Meeting of the Medford Comprehensive High School Building Committee - June 18, 2026

Meeting of the Medford Comprehensive High School Building Committee

Date/Time

June 18, 2026
6:30 p.m. at Bistro 489 at Medford High School

Location

Please be advised that there will be a Full Committee meeting of the Medford Comprehensive High School Building Committee (MCHSBC) in person at Bistro 489 at Medford High School, 489 Winthrop Street and via remote participation.

This meeting can be viewed live on the Medford Public Schools YouTube channel or via Medford Community Media on your local cable channel (Comcast Channel 9, 8 or 22 and Verizon Channel 43, 45 or 47). The meeting will be recorded.

Agenda

Agenda for the June 18, 2026 Meeting of the Medford Comprehensive High School Building Committee

Zoom Link

https://mps02155-org.zoom.us/j/99900399763?pwd=BjayCuDJbW1o5hAvwvyK1LiPAzQeUR.1

Public Comment Rules

  1. Public comment will be limited to three (3) minutes per individual and will be limited to those matters on the agenda.
  2. Speakers may only speak once on each topic.
  3. The chair may limit comments to two (2) minutes based on the number of individuals wishing to speak. The chair will announce the time limit before the public comment period at every meeting.

The public is encouraged to reach out in the following ways:

  • Questions regarding the project for an official response by the project team: mhsproject@medford.k12.ma.us
  • Comments or perspectives you would like to share with all members of the MCHSBC. Emails received will be auto-forwarded to all members of the SBC: mchsbc@medford.k12.ma.us

Complete Agenda

I. Roll Call

II. Approval of 6.10.26 Meeting Minutes

III. Be it resolved that the MCSBC authorizes the following space efficiencies to be incorporated into the PSR submission. Space efficiencies were identified through conversations that have begun to plan program adjacencies within our CTE programs. - Offered by Dr. Suzanne Galusi and Jenny Graham

Item #

Description of Proposed Change

Δ SF

Change to Ed Plan?

Efficiency / Reduction

Cluster CTE Toilet Rooms for Two Adjacent Shops

 

1

Metal Fab & Robotics

-130 sf

No

Efficiency

2

CCL & Carpentry

-130 sf

No

Efficiency

3

Electrical & Plumbing

-130 sf

No

Efficiency

4

Eliminate Biotechnology Dedicated Toilet Room

-60 sf

No

Efficiency

Cluster CTE Changing Rooms for Two Adjacent Shops

 

5

Metal Fab & Robotics

-170 sf

No

Efficiency

6

CCL & Carpentry

-170 sf

No

Efficiency

7

Electrical & Plumbing

-170 sf

No

Efficiency

Eliminate Loft Storage Area - Stock Storage on Shop Floors

8

Auto Tech, Carpentry, CCL & Metal Fab

-2,000sf

No

Efficiency

9

Reduce size of CTE Shop Related Rooms from 950 SF to 850 SF (all besides Cosmo & Business/Marketing)

-1,700 sf

No

Efficiency

Eliminate CTE Shop Offices - Lockable Instructor Desks on Shop Floors

10

Small Staff Offices (100 SF)

-700 sf

No

Efficiency

11

Medium Staff Offices (120 SF)

-1,320 sf

No

Efficiency

IV. Approval to Authorize LeftField to Submit the PSR Submission to the MSBA

V. Approval of the CM at Risk Request for Qualification (RFQ)VI. Upcoming Meetings

VII. Adjournment